Gantt: launch timeline
This timeline makes dependencies, slippage, and the current date clear during planning.
14Gantt: launch timelineInteractive
V3.0 launch
Today: September 28 2026
| Workstream | Owner | Start | Planned end | Actual end | Complete % |
|---|---|---|---|---|---|
| Item-master intake | R. Kim | September 07 2026 | September 28 2026 | September 28 2026 | 100 |
| Field mapping freeze | D. Novak | September 14 2026 | September 28 2026 | September 28 2026 | 100 |
| Validation rules | S. Ibrahim | September 28 2026 | October 19 2026 | October 19 2026 | 70 |
| ERP crosswalk | L. Alvarez | September 16 2026 | September 30 2026 | October 05 2026 | 45 |
| Hospital enablement | T. Brandt | October 05 2026 | October 24 2026 | October 24 2026 | 80 |
| First production sync | R. Kim | November 02 2026 | November 03 2026 | November 03 2026 | 0 |